Project 06-202 |
|
Research Lab Air Handler Unit
Installation
Wilkes-Barre, PA |
| Owner |
| Wilkes-Barre VAMC |
| |
Structural analysis of
existing ninth floor framing to verify capacity to support two proposed
air handling units. Analyzed floor framing system using 60 PSF floor
live load and an 80 PSF dead load in combination with the 450 and 350
pound loads applied by proposed units. We determined the existing floor
framing system had adequate load-carrying capacity and designed hanger
support details.
Estimated Construction Cost: $500,000.00 |
|